First Balfour grew rapidly in the 2010s, as can be seen in some of its achievements listed here.
2010
First Balfour, in a joint venture with DMCI, completes the LRT-1 North Extension project with the operation of the Balintawak Station in March and the Roosevelt Station in October
The company is awarded the construction of the 111-ML N. Domingo Water Reservoir, the largest concrete water reservoir structure in the Philippines
2011
First Balfour receives two accolades from Texas Instruments (TI) Philippines Inc.—a recognition for achieving a Zero Accident record in a Building Expansion Project in Clark, the best safety record compared with 12 other TI projects of similar size and type around the world; and the 2011 Texas Instruments Regional Supplier Recognition Award, the only construction service provider of TI worldwide given the award for the year
Transfers to its new corporate facility in Sucat, Parañaque which integrates its corporate head office with its plant operations division.
2012
The corporate office in Parañaque is awarded by the Philippine Green Building Council as its very first Building for Ecologically Responsive Design Excellence (BERDE)Certified Building in Design
2014
Completes the Burgos Wind Farm projects, allowing its customer to be the first renewable energy project proponent to win the feed-in tariff race
2015
Delivers the largest solar farm in Mindanao, the 12-MW Kirahon Solar Farm in Cagayan de Oro
Sets up Therma One Transport Corporation in March to take advantage of opportunities that exist in the transportation of heavy equipment and materials to various parts of the Philippines
2016
Completes the NLEX Road Widening Project which adds one lane each on the 23-km. stretch between Santa Rita, Bulacan to San Fernando, Pampanga Completes two ePLDT Vitro Data Centers in Makati, the largest in the Philippines, and in Clark in Pampanga
2017
Order backlog reaches a historical high with the award of two big-ticket projects: the Cebu-Cordova Link Express way project and the Novaliches-Balara Aqueduct project First Balfour is among the first construction companies that transitions to the ISO 9001:2015 standard for quality management. The company has been ISO 9001-certified since 2002 and ISO 14001- and OHSAS 18001-certified since 2003 Achieves the Investors in People (IiP) Silver accreditation and still remains the first and only IiP-certified engineering and construction company in the Philippines